Jabodebek LRT Progress June 2021
16 Juli 2021
As of June 25, 2021, progress has reached 85.61%.
Currently, the first Jabodebek LRT train has been placed at Harjamukti Station, Cibubur and has begun to be tested for the Cililitan Long Range. There are 25 trains that have been parked along service line I.
In the Cawang-Cibubur service cross, it reached 93.85%.
Meanwhile, the Cawang-Dukuh Atas cross reached 85.92%.
Traffic on Cawang-East Bekasi traffic reached 91.24%.
For Depot, it reached 46.79%